The steam-blowing operation for the secondary-circuit main steam piping of Hainan Changjiang Nuclear Power Unit 4 has been successfully completed.
On July 23, the "shock blow" cleaning operation for the secondary-circuit main steam piping of Unit 4 at the Hainan Changjiang Nuclear Power Plant—undertaken by China Nuclear Industry Fifth Construction Co., Ltd.—was successfully completed. The
2026-07-27
The first nuclear steam turbine roll test for Unit 3 of the Huaneng Changjiang Nuclear Power Project (Phase II) was successfully completed.
At 07:56 on July 24, Unit 3 of the Huaneng Hainan Changjiang Nuclear Power Plant—the first large-scale pressurized water reactor (PWR) nuclear power project controlled and constructed by China Huaneng Group Co., Ltd., and the first "Hualong One"
2026-07-27