Search Results

Keyword:Zhejiang

First Backup Emergency Diesel Generator of Hualong One Officially Available at Sanao Nuclear Power Unit 2

First Backup Emergency Diesel Generator of Hualong One Officially Available at Sanao Nuclear Power Unit 2

On October 2, the first backup emergency diesel generator (9LHW) of Hualong One completed the replacement grid connection test at Sanao Nuclear Power Unit 2 and was officially put into service. The equipment can replace any one of the original 12 emergency diesel generators (EDGs) in Phase I and Phase II projects, significantly improving the redundancy, reliability, and maintenance flexibility of the plant's emergency power supply. Sanao Nuclear Power Phase I and Phase II each have 3 emergency busbars, with one EDG configured for each busbar. However, due to the absence of cross-power supply for loads, the preventive maintenance windows of the original units were concentrated, affecting the overhaul schedule. Since 2021, Cangnan Nuclear Power has promoted the project of adding backup diesel generators, improving from the design source, building a new backup emergency diesel generator building (BDD), and constructing corridors and cables connected to each unit...

2026-10-03

CGN Cangnan No. 3 Nuclear Power Co., Ltd. Established

CGN Cangnan No. 3 Nuclear Power Co., Ltd. Established

According to Qichacha APP, CGN Cangnan No. 3 Nuclear Power Co., Ltd. was recently established, with its business scope including: heat production and supply; technology import and export; goods import and export, etc. Qichacha equity penetration shows that the company is jointly held by China General Nuclear Power Corporation, Zhejiang Zheneng Electric Power Co., Ltd., and Zhejiang Geely Industrial Investment Holding Co., Ltd., a wholly-owned subsidiary of Zhejiang Geely Holding Group Co., Ltd., among others.

2026-10-03

CGN Environmental Protection and Cangnan Nuclear Power Sign a New Round of General Contracting Agreement for Nuclear Environmental Protection Business

CGN Environmental Protection and Cangnan Nuclear Power Sign a New Round of General Contracting Agreement for Nuclear Environmental Protection Business

Recently, CGN Environmental Protection and Cangnan Nuclear Power officially signed a new round of general contracting agreement for nuclear environmental protection business. This marks a comprehensive upgrade of their cooperation from version 1.0 to version 2.0, and also a substantive implementation of the Group's deepening reform strategy in the field of nuclear environmental protection. Zhan Weihua, Deputy Party Secretary and General Manager of Cangnan Nuclear Power, and Qin Geng, Party Committee Member and Chief Accountant; Ren Junhua, Deputy Party Secretary and General Manager of CGN Environmental Protection, Lu Shubao, Party Committee Member and Deputy General Manager, and Yang Wei, Party Committee Member and Deputy General Manager attended the signing ceremony. In 2025, CGN Environmental Protection transitioned toward nuclear environmental protection business and signed the first round of general contracting agreements with multiple plants. Over the past year, the company has continuously honed its capabilities in business undertaking and execution, and is accelerating the construction of an integrated...

2026-10-02

Construction of BOP Sub-item Installation Works for Units 1 and 2 of Zhejiang Jinqimen Nuclear Power Plant Officially Commences

Construction of BOP Sub-item Installation Works for Units 1 and 2 of Zhejiang Jinqimen Nuclear Power Plant Officially Commences

On September 29, the BOP sub-item installation works (Lot 1 and Lot 2) for Units 1 and 2 of Zhejiang Jinqimen Nuclear Power Plant, contracted by Beijing Zhongyan Dadi Technology Co., Ltd. (hereinafter referred to as Zhongyan Dadi), officially commenced, marking the full launch of the project construction. Jinqimen Nuclear Power Plant is located in Xiangshan County, Ningbo City, Zhejiang Province. It is a benchmark clean energy project under national key planning. Once fully completed, its annual power generation capacity will reach 55 billion kWh, which is of great strategic significance to the optimization of the energy structure and green low-carbon transformation in the Yangtze River Delta region. The BOP (nuclear power plant supporting facilities) sub-item is an important foundation for ensuring the safe and stable operation of nuclear power units, and its construction precision and quality control standards are far...

2026-09-30

Construction Site Leveling and Excavation Kicks Off for Hualong One Version 2.0 Demonstration Project of Zhejiang Jinqimen Nuclear Power Phase II

Construction Site Leveling and Excavation Kicks Off for Hualong One Version 2.0 Demonstration Project of Zhejiang Jinqimen Nuclear Power Phase II

On the morning of September 9, Zhejiang Jinqimen Nuclear Power held a mobilization meeting for high-quality construction of the Hualong One Version 2.0 demonstration project of Phase II, marking the full launch of site leveling and excavation work for Phase II. At the event, Yao Zhaohong, General Manager of Jinqimen Nuclear Power, presented the flag to the Party Member Commando Team for High-Quality Commencement of the Demonstration Project. Zhong Hua, Party Secretary and Chairman of Jinqimen Nuclear Power, delivered a mobilization speech and announced the start of site leveling and excavation work. At 11:11, the first blast for the main excavation of Phase II was successfully detonated, marking that the project construction has entered a stage of accelerated advancement. The mobilization meeting stated that Jinqimen Nuclear Power undertakes the task of constructing the Hualong One Version 2.0 demonstration project, and all participating units and builders must fulfill safety and quality responsibilities, adhere to safety first and quality first, steadily advance project construction, and build a high-standard "New Quality Hualong Demonstration Project."

2026-09-10

First Application and Verification of Intelligent Monitoring and Adjustment System for Nuclear Power Plant Personnel Status at "Hualong One" Nuclear Power Plant

First Application and Verification of Intelligent Monitoring and Adjustment System for Nuclear Power Plant Personnel Status at "Hualong One" Nuclear Power Plant

On September 4, CGN Engineering, in collaboration with Cangnan Nuclear Power, successfully completed the testing, verification, and on-site data collection of the Intelligent Monitoring and Adjustment System for Nuclear Power Plant Personnel Status at the San'ao Nuclear Power Base. The CGN Engineering departments participating in this testing and verification included CGN Design Institute, the National Key Laboratory of Nuclear Power Safety Technology and Equipment (hereinafter referred to as the National Key Laboratory), CGN Engineering Cangnan Project Department, and Huasheng Technology. This joint test marks an important milestone in the project's transition from technology research and development to engineering application, providing key technical support for the quantitative analysis transformation of human factors safety management in China's nuclear power industry. The system, built upon the personnel fatigue status monitoring principle prototype developed under the Intelligent Nuclear Power strategic special project, has been iteratively improved with continuous support from the Yangjiang Chuangbao High-tech Research Project and the National Key Laboratory research projects, and has now evolved into a mature product suitable for engineering and large-scale application. Previously, relevant functional modules of the system had been deployed and data collected in applications such as human factors verification in the main control room of Yangjiang Nuclear Power Base and simulator training at Taishan Nuclear Power Base. The on-site testing and data collection at the San'ao Nuclear Power Base further verified the system's environmental adaptability and reliability across multiple nuclear power base scenarios, laying a solid foundation for subsequent industry-wide promotion and application.

2026-09-05

Qinshan Nuclear Power Completes Overhaul Validation of Grille Cleaning Robotic Arm

Qinshan Nuclear Power Completes Overhaul Validation of Grille Cleaning Robotic Arm

The grille cleaning robotic arm, an integrated system of UAV-based intelligent inspection and robotic arm automatic cleaning independently developed by the Mechanical Team of the Fourth Maintenance Division at Qinshan Nuclear Power, recently completed on-site validation during the Unit 2 312 overhaul at Qinshan Phase II. Designed for seawater system intake grille cleaning scenarios, this equipment transforms the original manual operation requiring entry into deep wells into an unmanned operation conducted under ground-based remote monitoring. The intake grille serves as a critical barrier for the cooling water system of a nuclear power plant, and its unobstructed condition is directly related to the stable operation of the unit. In traditional cleaning methods, workers were required to enter narrow shafts more than twenty meters underground to perform inspection and cleaning in confined spaces, which involved high labor intensity, low efficiency, and safety risks such as falls from height...

2026-09-03

Zhejiang Jinqimen Nuclear Power Unit 1 Pressurizer Relief Tank Successfully Hoisted into Place

Zhejiang Jinqimen Nuclear Power Unit 1 Pressurizer Relief Tank Successfully Hoisted into Place

On August 30, the pressurizer relief tank, a major nuclear island equipment item of Unit 1 at Zhejiang Jinqimen Nuclear Power Plant, contracted by China Nuclear Industry Fifth Construction Co., Ltd. (CNF), was successfully hoisted into place. The entire hoisting process was smooth and orderly, with overall safety and quality under control. This hoisting has laid a solid foundation for the subsequent installation of main nuclear island equipment and the construction of the primary loop system. The pressurizer relief tank is an important auxiliary equipment of the reactor coolant system in a nuclear power plant. Its main function is to collect and condense the high-temperature and high-pressure steam discharged from the pressurizer safety valves, ensuring the safe and stable operation of the reactor system. The relief tank hoisted this time is pre-installed equipment in the nuclear island. The main body of the equipment is heavy in weight and large in size, with limited hoisting workspace. After being hoisted into place, it needs to be placed in the nuclear island building for a long period, and subsequent construction will be constrained by space, making it necessary to introduce the equipment precisely within the civil construction window period.

2026-09-02

Qinshan Nuclear Power Plant Unit 2 Outage 218 Officially Commences

Qinshan Nuclear Power Plant Unit 2 Outage 218 Officially Commences

At 2:20 AM on September 1, Unit 2 of Qinshan Phase II was disconnected from the East China Power Grid, marking the official commencement of Outage 218. This outage is a Category C overhaul for Unit 2 of Qinshan Phase II. In addition to the routine annual overhaul items such as reactor coolant system head removal and installation, fuel handling, SG eddy current inspection and flushing, it also includes important special tasks such as generator rotor removal, insertion and inspection, diesel generator excitation system renovation, PSR weakness anti-boron dilution modification, reactor coolant system automatic makeup and residual heat removal eddy current detection function, and nuclear island low-voltage switchgear renovation. The planned items for this outage total 6,119: including 3,764 preventive items, 171 strategic maintenance items, 789 periodic tests, 133 modification work orders, and 1,262 other types of work.

2026-09-01

China Isotope & Radiation Plans to Invest RMB 400 Million in Zhejiang Nuclear Technology Application Industry Fund

China Isotope & Radiation Plans to Invest RMB 400 Million in Zhejiang Nuclear Technology Application Industry Fund

China Isotope & Radiation Corporation announced on August 28 that its board of directors has approved entering into a partnership agreement with CNNC, CNNC Capital, CNNC Fund, National Industry Investment Fund, Zhejiang Venture Capital Guidance Fund, Jiaxing Changchuang Industrial Investment, and Haiyan County State-owned Capital Investment to jointly establish CNNC (Zhejiang) Nuclear Technology Application Industry Investment Fund Partnership (Limited Partnership). According to the announcement, the fund will be registered in Jiaxing City, Zhejiang Province, with partners intending to subscribe to a total capital contribution of RMB 3 billion. Among them, China Isotope & Radiation plans to contribute RMB 400 million from internal resources, accounting for 13.33% of the fund's total subscribed capital; CNNC Fund, as the general partner, plans to contribute RMB 30 million, accounting for 1%; the National...

2026-08-29

Qinshan Nuclear Power Membrane Deoxygenation Retrofit Project Put into Operation

Qinshan Nuclear Power Membrane Deoxygenation Retrofit Project Put into Operation

Recently, the membrane deoxygenation retrofit project at Qinshan Nuclear Power completed commissioning and was put into operation. The project applies membrane deoxygenation technology to the auxiliary feedwater system (ASG) and reactor boron and water makeup system (REA) of Units 1 and 2 at Qinshan Nuclear Power Plant Phase II, optimizing and upgrading the original deoxygenation process. Units 1 and 2 of Qinshan Phase II originally adopted thermal deoxygenation. During long-term operation, this method presented issues such as insufficient redundancy in single-train equipment operation, high temperature and humidity on site, and potential exceedance of auxiliary feedwater tank temperature limits during summer peak temperature periods. To enhance system operational reliability, Qinshan Nuclear Power initiated relevant technical retrofits, introducing membrane separation packaged units to form a parallel standby configuration with the original thermal deoxygenation system, allowing flexible switching...

2026-08-28

Sichuan Huadu Nuclear Energy Wins Control Rod Drive Mechanism Orders for 4 Nuclear Power Units

Sichuan Huadu Nuclear Energy Wins Control Rod Drive Mechanism Orders for 4 Nuclear Power Units

On August 24, news came from Sichuan Huadu Nuclear Equipment Manufacturing Co., Ltd., located in Dujiangyan, Chengdu, Sichuan, that the company has won the orders for control rod drive mechanisms for 4 units among the first batch of nuclear power units approved for construction during the 15th Five-Year Plan period in China, with a total new contract value of 504 million yuan. The winning projects include Units 3 and 4 of Zhejiang Jinqimen Nuclear Power Plant, as well as Units 1 and 2 of Phase I of Liaoning Zhuanghe Nuclear Power. According to the previous approval arrangement by the State Council Executive Meeting, the new batch of nuclear power projects involves a total of 4 projects and 8 units, including Phase II of Zhejiang Jinqimen Nuclear Power, Phase III of Guangdong Taipingling Nuclear Power, Phase I of Liaoning Zhuanghe Nuclear Power, and Phase I of Shandong Laiyang Nuclear Power, all adopting China's self-developed third-generation nuclear power technology...

2026-08-27

Huzhou, Zhejiang Launches Phase I "Drug-Device Combination" Clinical Trial for the Province's First BNCT System

Huzhou, Zhejiang Launches Phase I "Drug-Device Combination" Clinical Trial for the Province's First BNCT System

Recently, the Boron Neutron Tumor Treatment Center at Huzhou Hospital Affiliated to Zhejiang University School of Medicine has drawn attention with the introduction of the province's first Boron Neutron Capture Therapy (BNCT) system. Previously, the system had already initiated a Phase I BNCT drug-device combination clinical trial. According to the system developer, Huapeng Neutron Technology (Hangzhou) Co., Ltd., BNCT is a radiotherapy technique combining drugs and devices, with its core lying in the coordinated use of boron-containing drugs and neutron irradiation. After entering the human body, the boron-containing drug can be absorbed by tumor cells; subsequent neutron beam irradiation triggers a localized reaction to achieve targeted radiotherapy against tumor cells. Unlike conventional radiotherapy, which typically employs fractionated irradiation over a longer treatment course, BNCT emphasizes selective targeting of tumor cells, aiming to reduce damage to surrounding healthy tissues and lower radiotherapy-related side effects such as hair loss and immunosuppression.

2026-08-27

Qinshan Nuclear Power Receives On-Site Visit for WANO Enhanced Performance Monitoring and Achieves Highest Rating

Qinshan Nuclear Power Receives On-Site Visit for WANO Enhanced Performance Monitoring and Achieves Highest Rating

Recently, experts from the World Association of Nuclear Operators (WANO) Tokyo Center and Shanghai Office visited Qinshan Nuclear Power to conduct an on-site Enhanced Performance Monitoring (ePM) assessment for its nine units. Based on a comprehensive evaluation, the WANO on-site visit team unanimously concluded that Qinshan Nuclear Power has demonstrated steady overall performance improvement in recent years and currently operates at the industry's highest "benchmark" level, with expectations that performance across key areas will remain stable or continue to improve over the next six months. Additionally, WANO experts conducted follow-up evaluations on selected Areas for Improvement (AFIs) and Significant Operating Experience Report (SOER) recommendations arising from the 2025 WANO peer review of Qinshan Nuclear Power's nine units, deeming the overall results satisfactory. At a summary meeting held on August 20...

2026-08-22

Construction of the conventional island raft foundation slab for Unit 2 of Zhejiang Jinqimen Nuclear Power Plant completed

Construction of the conventional island raft foundation slab for Unit 2 of Zhejiang Jinqimen Nuclear Power Plant completed

At 3:36 on August 20, the raft foundation slab pouring for the conventional island of Unit 2 at Zhejiang Jinqimen Nuclear Power Plant was successfully completed. With the final batch of concrete precisely placed into the formwork, the main structure construction of the conventional island for this unit was officially initiated. The concrete supply for this pouring operation was provided by CNNC Concrete Xiangshan Branch. The operation lasted 29 hours and 20 minutes, with a cumulative supply of over 4,000 cubic meters of concrete, achieving continuous and stable material delivery. The maximum pouring thickness at this section was 3 meters, with a height difference of 7 meters at the variable cross-section locations, and the structural design service life is 60 years. The project features large-volume, high-intensity construction characteristics, compounded by the rainy climate conditions on site, imposing stringent requirements on concrete supply continuity, delivery stability, and temperature control precision.

2026-08-21

Baidu
map