The first concrete pouring for the nuclear island of Unit 2 of State Power Investment Corporation (SPIC) Guangxi Bailong Nuclear Power Project was successfully completed.

The first concrete pouring for the nuclear island of Unit 2 of State Power Investment Corporation (SPIC) Guangxi Bailong Nuclear Power Project was successfully completed.

The first concrete pouring for the nuclear island of Unit 2 of SPIC Guangxi Bailong Nuclear Power Project was completed at 16:07 on September 30, after 69 hours and 40 minutes of continuous work. A total of 6,732.5 cubic meters of concrete was used for this pouring, marking another important milestone for the project after the FCD achievement for the nuclear island of Unit 1. Phase I of the Bailong Nuclear Power Project plans to build two CAP1000 nuclear power units. These two units adopt independently designed and domestically manufactured Generation III passive nuclear power technology, with each unit having a capacity of up to 1.25 million kilowatts. At present, Unit 1 has entered the construction and installation stage, and the steel containment vessel bottom head, CA20, CV1R, CA01...

2026-09-30

Unit 2 of State Power Investment Corporation (SPIC) Guangxi Bailong Nuclear Power Project starts construction

Unit 2 of State Power Investment Corporation (SPIC) Guangxi Bailong Nuclear Power Project starts construction

At 18:27 on September 27, the nuclear island of Unit 2 of State Power Investment Corporation (SPIC) Guangxi Nuclear Power Bailong Nuclear Power Project began its first concrete pour (FCD), marking that Phase I of the Bailong Nuclear Power Project has shifted from single-unit construction to a new stage of comprehensive dual-unit construction. The FCD for Unit 2 of the Bailong Nuclear Power Project adopted a single-side pushing continuous one-time integral pouring method, with approximately 6,637 cubic meters of concrete planned to be poured over approximately 58 hours. In view of the multiple overlapping construction difficulties such as the large bottom slab size, irregular shape, and high difficulty of temperature control and curing, the project team prepared a special construction plan in advance and implemented all-round safeguard measures. The single-side pushing pouring path and process parameters were optimized, and the owner, supervisor and general contractor exercised full-process on-site supervision and control

2026-09-28

CA01 Module of Unit 1 at Guangxi Bailong Nuclear Power Plant Successfully Hoisted into Position in the Nuclear Island

CA01 Module of Unit 1 at Guangxi Bailong Nuclear Power Plant Successfully Hoisted into Position in the Nuclear Island

On August 29, the CA01 module of Unit 1 at the Bailong Nuclear Power Plant of SPIC Guangxi Nuclear Power was precisely positioned, marking a new phase of parallel civil construction and installation in the nuclear island. ▲On August 29, the hoisting operation of the CA01 module of Unit 1 at the Guangxi Bailong Nuclear Power Plant of SPIC was proceeding in an orderly manner. The CA01 module is located in the reactor building of the nuclear island and serves as the installation room for main equipment such as the reactor pressure vessel, steam generators, and pressurizer. The module is T-shaped in overall form, with external dimensions of 28 meters in length, 29 meters in width, and 24 meters in height. It consists of 47 sub-modules, with a total lifting weight of approximately 1,167 tons, making it the largest and heaviest structural module in the nuclear island. The hoisting operation commenced at 8:07 a.m. and, after a series of maneuvers including lifting, hovering, slewing, lowering, and adjustment, was successfully positioned at 12:58 p.m., with the entire process being safe, controllable, stable, and orderly.

2026-08-31

Steel Containment Vessel Ring 1 of Unit 1 at Guangxi Bailong Nuclear Power Plant Successfully Hoisted into Place

Steel Containment Vessel Ring 1 of Unit 1 at Guangxi Bailong Nuclear Power Plant Successfully Hoisted into Place

At 11:38 on August 16, after 4 hours and 01 minutes of continuous and stable operation, the steel containment vessel ring 1 (CV1R) of the nuclear island of Unit 1 at Guangxi Bailong Nuclear Power Plant was successfully hoisted into place. This hoisting marks another successful installation of a key module following the CVBH and CA20 modules for Unit 1 of Bailong Nuclear Power Plant, signifying a critical breakthrough in the construction of the main structure of the nuclear island of Unit 1. The steel containment vessel consists of five major modules: the bottom head, the intermediate cylindrical shell (rings 1 to 3), and the top head, serving as the third physical safety barrier of the reactor. The CV1R hoisted this time is the core component with the largest volume and heaviest weight among the five major components of the steel containment vessel, measuring approximately 15.5 meters in height and up to 39.6 meters in maximum inner diameter, integrating equipment...

2026-08-17

SPIC Nuclear Conventional Island Quality Supervision Sub-station Conducts Pre-FCD Supervision and Inspection on Unit 2 of Guangxi Bailong Nuclear Power Plant

SPIC Nuclear Conventional Island Quality Supervision Sub-station Conducts Pre-FCD Supervision and Inspection on Unit 2 of Guangxi Bailong Nuclear Power Plant

Recently, the Nuclear Conventional Island Engineering Quality Supervision Sub-station of State Power Investment Corporation (hereinafter referred to as the SPIC Sub-station) completed the first and pre-FCD quality supervision and inspection of the conventional island of Unit 2 of Phase I of the Guangxi Bailong Nuclear Power Plant. The inspection adopted a cross-supervision model, coordinated by the Nuclear Conventional Island Engineering Quality Supervision Station, with the directly affiliated project station organizing a supervision team of senior industry experts, and the SPIC Sub-station providing full coordination and support throughout the process. This initiative aims to break long-standing inertial thinking and leverage external perspectives to identify management blind spots and quality hazards that may have been overlooked. Yin Jingfeng, Executive Deputy Director of the Nuclear Conventional Island Engineering Quality Supervision Group, attended the event and made work arrangements, with project leaders from the construction unit and all participating units fully involved in the supervision and inspection.

2026-08-11

First Concrete Pour (FCD) Successfully Completed for the Conventional Island of Unit 2 at Guangxi Bailong Nuclear Power Plant

First Concrete Pour (FCD) Successfully Completed for the Conventional Island of Unit 2 at Guangxi Bailong Nuclear Power Plant

At 10:06 on August 9, after 38 hours and 46 minutes of continuous effort, the First Concrete Pour (FCD) for the conventional island of Unit 2 at the SPIC Guangxi Bailong Nuclear Power Plant was successfully completed, marking the full commencement of the main construction phase for the conventional island. The basement floor slab of the conventional island of Unit 2 adopts an integral raft foundation, divided into 9 construction zones using the sequence method. This concrete pour covered Zone 1, starting at 19:20 on August 7, with a cumulative pour of 1,732 cubic meters of concrete, conducted safely and orderly throughout the process. Since July, Typhoon Maysak directly struck Fangchenggang, bringing successive storms, followed by days of high temperatures at the Bailong nuclear site, posing significant challenges to on-site construction. In response...

2026-08-10